The initial 9 km DND-Jaitpur section of the Delhi-Mumbai Expressway is nearing completion, with 94.23% physical progress reported. The government informed Lok Sabha that this segment is slated for a June 2026 finish, despite minor delays attributed to irrigation department approvals. The broader expressway project has already seen an investment of Rs 71,718 crore.